A taste of things to come? - UK smart meter data access

correct, the hoops the consumer has to jump through are typically

  • install PV
  • Get a MSC
  • Get a letter of authorisation from you DNO
  • Ask you supplier for export tariff
  • wait for export mpan
  • wait for smart meter to be commissioned with export mpan
  • wait for supplier to figure out how to read your export data
  • wait for their (sometimes quarterly payment cycle to complete)
  • calculate if your payment was correct
  • raise a compliant (potentially)

Only party joking but you won’t get paid for any export between steps 2-6